How Progressive Payments Work

When you buy a private home that is still being built, you do not pay the full price at once. The standard Sale and Purchase Agreement sets out a payment schedule tied to construction: 5% to book, another 15% within 8 weeks, then 10%, 10%, 5%, 5%, 5% and 5% as building stages are finished, 25% when the Temporary Occupation Permit is issued, and the last 15% on legal completion.

Your own cash and CPF go in first. Once your share is used up, the bank pays the developer directly at each stage, and your loan grows a step at a time. You pay instalments only on what has been drawn, so they begin low and rise as the building goes up.

This matters for cash flow. A buyer who is still paying for a current home needs to know when each jump arrives, not just the final figure. Change the timing boxes to match the developer's expected dates and print the table for the client.